The Project includes main lines and sewage networks. The Excavation was done by Microtunneling method.
The mainline installed are Reinforced Concrete Pipe of diameter 1600 mm. with a total length of 9,800 meter.
Location: Madinah, Saudi Arabia
Client: Roshn
Year of Award: 2006
Status: Completed – 2008